Agenda Item
C.11. 23-558 Adopt a resolution determining Conco West, Inc. as the lowest responsive and responsible bidder for the Well 29 TCP Treatment Project Capital Improvement Program (CIP) No. 22058; award the construction contract to Conco West, Inc. in the amount of $3,278,000 for base services; approve the professional services agreement with Brown & Caldwell for construction management and inspection services in the amount of $344,510; approve a project contingency not-to-exceed 10% of $362,251; authorize the City Manager or designee to approve change orders and task orders up to the total project cost, apply for permits, apply for State and Federal grants, solicit project funding support, and take all appropriate actions necessary to carry out the purpose and intent of the resolution.