Meeting Time: September 03, 2024 at 6:00pm PDT

Agenda Item

C.4 24-435 Adopt a resolution determining C. Overaa & Company as the lowest responsive and responsible bidder for the WQCF Capacity Improvement Projects Flow Split Repair CIP 23002, IMLR Pump Replacement CIP 23003, Process Aeration Control CIP 23004, and Zone B Mixing System CIP 23005; awarding the construction contract to C. Overaa & Company in the amount of $11,475,000; approving a Professional Services Agreement for construction management and inspection services with Carollo Engineers, Inc. in the amount of $991,070; approving a project contingency of 10% not-to-exceed $1,250,000; and authorizing the City Manager or designee to take all appropriate actions necessary to carry out the purpose and intent of the resolution.